Supplier:
xxxxxxxxx xxxxxxxx
|
|
|
|
Audit performed by:
xxxxxxxxx, APC, Shenzhen
|
|
|
|
Date:
08-04-2010
|
|
|
|
|
|
|
|
|
|
|
4.1.2
|
Organization
|
|
|
|
|
|
|
|
Does supplier have a Quality Manager?
Name:
|
|
|
|
Is the Quality Manager independent of the production?
|
|
|
|
|
|
|
4.2
|
Quality Management System
|
|
|
|
|
|
|
|
Does supplier have a quality policy?
|
|
|
|
Does supplier have a manual for quality?
|
|
|
|
Is the manual available for the staff?
|
|
|
|
Which quality approvals has the
supplier
last approval:
|
|
|
|
Which norm approval has
supplier
last: approval:
|
|
|
Which environment
approval
last: approval:
|
|
|
|
|
|
|
4.3
|
Contract rewiev
|
|
|
|
|
|
|
|
Will supplier accept a contractual obligation of quality?
|
|
|
|
Will supplier accept a contractual maximum percentage
of error?
AQL
|
|
|
|
|
|
|
4.4
|
Design Control
|
|
|
|
|
|
|
|
Is the function and construction of prototypes
described and compared to specifications and
documentations?
|
|
|
|
Are samples send to customer?
|
|
|
|
|
|
|
4.5
|
Document and data control
|
|
|
|
|
|
|
|
Is there a proceduce that secures the use of newest and
updated specification?
|
|
|
|
Is there a proceduce that secures that specifications are
updated?
|
|
|
|
|
|
|
4.6
|
Purchasing
|
|
|
|
|
|
|
|
Has supplier a system securing, that subcontractors know
specifications and goals?
|
|
|
|
Does supplier make audit at the subcontractor?
|
|
|
|
Does supplier control raw materials, components and
semi-manufactured articles by incomming?
|
|
|
|
Can supplier garuantee, that main products, semi-manufacture
and processes wil not be sourced out,without customers
accept?
|
|
|
|
|
|
|
4.7.8
|
Purchasing and stock
|
|
|
|
|
|
|
|
Does supplier secure, that stock goods are not obsolete?
(eldest goods - first used)?
|
|
|
|
Does supplier secure, that electronic components are stocked
and handled in EMC protected environments?
|
|
|
|
Does supplier secure, that customer delivered components are
seperately stocked and marked with customers name?
|
|
|
|
|
|
|
4.9
|
Process control
|
|
|
|
|
|
|
|
Has supplier a process plan including control points and
described control equipment (control point plan)
|
|
|
|
Does supplier registrer the parametre of the processes.
|
|
|
|
|
|
|
4.10
|
Inspection and testing
|
|
|
|
|
|
|
|
Has the supplier:
|
|
|
|
a) incomming control?
|
|
|
|
1.random test?
|
|
|
|
2. 100%?
|
|
|
|
b) process control?
|
|
|
|
1. random test?
|
|
|
|
2. 100%?
|
|
|
|
c) outgoing control?
|
|
|
|
1.random test?
|
|
|
|
2. 100%
|
|
|
|
|
|
|
|
Supplier of EMS:
|
|
|
|
a) visual control/testing?
|
|
|
|
b) function testing?
|
|
|
|
c) in-circuit-test?
|
|
|
|
|
|
|
4.11
|
Control of inspection and measuring and test equipment
|
|
|
|
|
|
|
|
Does supplier have reference norms for calibration?
|
|
|
|
Does supplier have a turnus plan for calibration?
|
|
|
|
Are data of calibration registrated?
|
|
|
|
|
|
|
4.12
|
Inspection and test status
|
|
|
|
|
|
|
|
Has supplier:
|
|
|
|
a) A list over test equipment with measure precision?
|
|
|
|
b)Specification of acceptable - unacceptable result from
measuring?
|
|
|
|
c) A procedure for handling after rejection?
|
|
|
|
|
|
|
4.14
|
Corrective and preventive action
|
|
|
|
|
|
|
|
Does supplier have a procedure for:
|
|
|
|
a) Correction by process deviation?
|
|
|
|
b) Correction by product- and function deviation?
|
|
|
|
c) Correction by objection from customer?
|
|
|
|
d) Response to customer concerning corrigating handling by
obstruction?
|
|
|
|
|
|
|
4.15
|
Handling, storage, packaging, preservation and delivery
|
|
|
|
|
|
|
|
Does supplier have a procedure for:
|
|
|
|
a) Handling?
|
|
|
|
b) Storage?
|
|
|
|
c) Packaging?
|
|
|
|
d) Preservation?
|
|
|
|
e)Delivery?
|
|
|
|
|
|
|
4.16
|
Control of quality records
|
|
|
|
|
|
|
|
Does supplier have a procedure for:
|
|
|
|
identification, collection, indexing, access, filing,
storage, maintenance and disposition of quality records?.
|
|
|
|
|
|
|
4.17
|
Internal Quality audits
|
|
|
|
|
|
|
|
Does supplier have:
|
|
|
|
Procedure for internal audits?
|
|
|
|
Records from internal audits?
|
|
|
|
Record showing corrigating actions?
|
|
|
|
|
|
|
4.18
|
Training
|
|
|
|
|
|
|
|
Does supplier have documented procedure for educating and
training for personnel?
|
|
|
|
|
|
|
4.19
|
Service
|
|
|
|
|
|
|
|
Does supplier have a documented procedure for sevice
handling?
|
|
|
|
|
|
|
4.20
|
Statistical technics
|
|
|
|
|
|
|
|
Which statistical methods are used:
|
|
|
|
Mil std. 105-e
Niveau:
|
|
|
|
Others:
Niveau:
|
|
|
|
Others:
Niveau:
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Supplier must confirm, that no child under age of 18
participate in any kind of work in his production.
|
|
|
|
|
|
|
Signed
for supplier:
|
|
|
|
|
|
|
Signed for APC:
|
|
|
|
|
|